Chapter 6 of 89% of exam

Buildings, Structures, and Related Work

This section is about 9% of the exam: mechanical, plumbing and electrical systems, and demolition, disposal and recycling. For a Class A contractor these are usually pump stations, utility services and the demolition that clears the site. The PrepPass CSLB General Engineering (A) Study Guide covers this section in depth, with worked examples, named traps and a chapter quiz.

Systems

Equipment is submitted, installed, tested and turned over; energy is locked out during servicing.

Lockout/tagout
Stop, de-energize, block and tag equipment whose unexpected start or stored energy could injure someone.
Cal. Code Regs. tit. 8, 3314
Grounding
At least a No. 8 copper grounding conductor in conduit, bonded to metal components (Caltrans).
Caltrans Standard Specifications 2025, 87

Demolition

A written survey, utilities off, hazards purged, asbestos inspected and notified, then top-down demolition.

Asbestos notice
The NESHAP demolition notice is due 10 working days ahead even if no asbestos is found.
40 CFR 61.145
Free-standing walls
No wall section over one story or 12 feet left without lateral bracing.
Cal. Code Regs. tit. 8, 1735
Recycling
CALGreen requires at least 65% of nonhazardous C&D debris to be recycled or salvaged.
CalRecycle C&D guide

Keep going: the full CSLB Class A — General Engineering (Trade Exam) guide covers every section of the exam. CSLB Class A General Engineering — Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Studying in order?

Practice stays free. The full CSLB Class A — General Engineering (Trade Exam) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.

Get the book — $24.99
Report