Foundation and Concrete Construction

Foundation and Concrete Construction is about 11% of the exam: forms and falsework, placing and finishing concrete, and pilings and foundations. The PrepPass CSLB General Engineering (A) Study Guide covers this section in depth, with worked examples, named traps and a chapter quiz.

Forms and falsework

Formwork must withstand all loads; larger falsework is engineered and inspected before the pour.

Engineer required
Falsework over 14 feet high, with spans over 16 feet, or with traffic through it needs engineer-signed drawings.
Cal. Code Regs. tit. 8, 1717
Stripping
Forms stay until the concrete can support its weight and superimposed loads.
Cal. Code Regs. tit. 8, 1717

Placing and curing

Avoid segregation, consolidate promptly, and keep the concrete moist.

Free fall
No more than 8 feet without pipes, tubes or double belting.
Caltrans Standard Specifications 2025, 51-1.03D
Water cure
Keep concrete continuously wet for at least 7 days.
Caltrans Standard Specifications 2025, 90-1.03B
No retempering
Do not add water to partially hardened concrete.
Caltrans Standard Specifications 2025, 51-1.03D

Piles

Driven piles meet both resistance and tip elevation; CIDH piles are placed by tremie without vibration.

Driven piles
Impact hammer, at least 1/8 inch per blow at nominal resistance; no vibratory hammers.
Caltrans Standard Specifications 2025, 49-2.01C
CIDH
Tremie tubes at least 10 inches in diameter, kept in the concrete.
Caltrans Standard Specifications 2025, 49-3

Keep going: the full CSLB Class A — General Engineering (Trade Exam) guide covers every section of the exam. CSLB Class A General Engineering — Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Studying in order?

Practice stays free. The full CSLB Class A — General Engineering (Trade Exam) study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.

Get the book — $24.99
Report