70 questions
A sheet is 72 by 120 inches. Lites are 34 by 50 inches. In straight rows in either orientation, how many lites come from one sheet?
- a.5 lites
- b.6 lites
- c.3 lites
- d.4 lites✓
The first layout gives 2 across (72 ÷ 34) by 2 down (120 ÷ 50) for 4, and the rotated layout gives 1 across by 3 down for 3. Six would need three lites across 72 inches, which does not fit, and five would need a layout that neither orientation has room for.CSLB C-17 study guide 13E-17 (job-related calculations)
Lites of 18 by 24 inches are cut from a 60-by-80-inch sheet in straight rows, either orientation. How many fit on the sheet?
- a.8 lites
- b.10 lites
- c.9 lites✓
- d.12 lites
The first layout gives 3 across (60 ÷ 18) by 3 down (80 ÷ 24) for 9, and the rotated layout gives 2 by 4 for 8. Twelve would need four lites across 60 inches at 18 inches each, which does not fit, and ten needs a tenth lite that neither orientation has room for.CSLB C-17 study guide 13E-17 (job-related calculations)
A sheet costs $240 and yields 6 lites. What is the glass cost of one lite?
- a.$24
- b.$6
- c.$40✓
- d.$4
240 ÷ 6 = $40 per lite. The 6 is the number of lites, $4 divides by 60 instead of 6, and 24 shifts the decimal.CSLB C-17 study guide 13E-17 (job-related calculations)
A job costs $12,000. What is the price at a 15% markup?
- a.$12,180
- b.$13,800✓
- c.$14,118
- d.$13,500
Markup is on cost, so 12,000 × 1.15 = $13,800. The $14,118 is the price for a 15% margin, $12,180 adds 1.5 percent, and $13,500 adds 12.5 percent.CSLB C-17 study guide 13E-17 (job-related calculations)
A job is priced at $9,000 and the margin is 20 percent of the price. What is the cost?
- a.$7,200✓
- b.$10,800
- c.$11,250
- d.$7,500
The margin is 20 percent of price, so cost is 9,000 × 0.80 = $7,200. The $7,500 divides the price by 1.20 as if it were a markup, $11,250 divides the price by 0.80, and $10,800 adds the margin to the price.CSLB C-17 study guide 13E-17 (job-related calculations)
A job costs $5,000 and the price is $6,250. What markup does that represent?
- a.125 percent
- b.20 percent
- c.25 percent✓
- d.12.5 percent
Profit is $1,250 and 1,250 ÷ 5,000 = 25 percent of cost. Twenty percent is the margin on price, 12.5 percent halves the markup, and 125 percent is the price as a percentage of cost.CSLB C-17 study guide 13E-17 (job-related calculations)
A job costs $8,000 and the price is $10,000. What margin does that represent?
- a.20 percent✓
- b.25 percent
- c.125 percent
- d.80 percent
Profit is $2,000 and 2,000 ÷ 10,000 = 20 percent of price. Twenty-five percent is the markup on cost, 80 percent is the cost share of the price, and 125 percent is the price as a share of cost.CSLB C-17 study guide 13E-17 (job-related calculations)
A contractor wants a 25 percent margin on a $15,000 cost. What price is needed?
- a.$3,750
- b.$18,750
- c.$19,000
- d.$20,000✓
Price is cost ÷ (1 − 0.25) = 15,000 ÷ 0.75 = $20,000. The $18,750 is a 25 percent markup, $3,750 is 25 percent of cost, and $19,000 is a guess.CSLB C-17 study guide 13E-17 (job-related calculations)
Four glaziers work an 8-hour day at $55 per hour each. What is the labor cost for the day?
- a.$1,760✓
- b.$7,040
- c.$440
- d.$220
4 × 8 × 55 = $1,760. The $440 is one glazier for a day, $220 is one glazier for 4 hours, and $7,040 multiplies by four again.CSLB C-17 study guide 13E-17 (job-related calculations)
Material is $3,200, labor $2,400 and equipment $400. Overhead is 10 percent of direct cost and profit is 8 percent of cost plus overhead. What is the price?
- a.$6,480
- b.$7,128✓
- c.$6,600
- d.$7,080
Direct cost is $6,000, overhead is $600, cost plus overhead is $6,600, profit is $528, and the price is $7,128. The $7,080 figures profit on direct cost, $6,600 omits profit, and $6,480 adds 8 percent to direct cost with no overhead.CSLB C-17 study guide 13E-17 (job-related calculations)
Want these explained in order? CSLB C-17 Glazing Contractor Study Guide 2026 — PDF + EPUB, $24.99 · 14-day refund →
A two-person crew sets 6 lites per day. How many working days does a 45-lite job take?
- a.15 days
- b.9 days
- c.8 days✓
- d.23 days
45 ÷ 6 = 7.5, and a partial day is a working day, so 8. 9 adds a spare day, 15 treats the crew rate as per person, and 23 divides by two instead of six.CSLB C-17 study guide 13E-17 (job-related calculations)
Installing a lite takes 0.75 labor hours and there are 60 lites. Labor is $60 per hour. What is the labor cost?
- a.$3,600
- b.$270
- c.$2,700✓
- d.$45
60 × 0.75 = 45 hours, and 45 × 60 = $2,700. The 45 is hours, $3,600 uses a full hour per lite, and $270 shifts the decimal.CSLB C-17 study guide 13E-17 (job-related calculations)
A horizontal member spans 6 feet. What deflection limit does L/175 give?
- a.About 0.30 inch
- b.About 0.41 inch✓
- c.About 0.25 inch
- d.About 0.125 inch
The span is 72 inches and 72 ÷ 175 = 0.411 inch. The 0.30 inch is the L/240 value, 1/8 inch is the sill-under-glass limit, and 0.25 is not a rule value.Pilkington ATS-192 General glazing guidelines (2013)
A horizontal member spans 16 feet. Using the lesser of L/175 and 3/4 inch, what is the limit?
- a.0.75 inch✓
- b.1.10 inches
- c.0.55 inch
- d.0.125 inch
L/175 gives 192 ÷ 175 = 1.10 inches, which is more than 3/4 inch, so the cap of 3/4 inch controls. The 1.10 ignores the cap, 1/8 inch is another limit, and 0.55 is an 8-foot value.Pilkington ATS-192 General glazing guidelines (2013)
An opening is 30 by 40 inches. What should its diagonals measure?
- a.60 inches
- b.2,500 inches
- c.70 inches
- d.50 inches✓
The diagonal is √(30² + 40²) = √2,500 = 50 inches. The sum of the sides is 70, 60 is twice the short side, and 2,500 is the sum of the squares.CSLB C-17 study guide 13E-17 (measurements and calculations)
An opening's diagonals measure 84-1/4 and 84-7/16 inches. The guideline allows 1/8 inch of difference. What is the result?
- a.It passes, because the difference is under 1/4 inch
- b.It fails, because the difference is 3/16 inch✓
- c.It passes, because both diagonals are over 84 inches
- d.It fails, because the difference is 1/4 inch
84-7/16 minus 84-1/4 is 3/16 inch, which is more than 1/8 inch. A 1/4-inch allowance is not the guideline, the size of the diagonals does not matter, and the difference is not 1/4 inch.Pilkington ATS-192 General glazing guidelines (2013)
Using 25.4 millimeters per inch, what is a 6 mm lite closest to in nominal fractions?
- a.3/8 inch
- b.1/4 inch✓
- c.1/8 inch
- d.6 inches
6 ÷ 25.4 = 0.236 inch, closest to 1/4 inch. One-eighth is about 3 mm, 3/8 is about 10 mm, and 6 inches confuses the units.CSLB C-17 study guide 13E-17 (job-related calculations)
A framing member is 2.5 inches wide. What is that in millimeters?
- a.6.35 mm
- b.0.098 mm
- c.63.5 mm✓
- d.25.4 mm
2.5 × 25.4 = 63.5 millimeters. The 6.35 shifts the decimal one place, 0.098 divides by 25.4 instead of multiplying, and 25.4 is one inch.CSLB C-17 study guide 13E-17 (job-related calculations)
An insulating unit's air space is reported as 13.2 mm. What is that closest to in inches?
- a.1/2 inch✓
- b.1/4 inch
- c.1/8 inch
- d.3/4 inch
13.2 ÷ 25.4 = 0.52 inch, closest to 1/2 inch. A quarter inch is about 6 mm, 3/4 inch is about 19 mm, and an eighth is about 3 mm.CSLB C-17 study guide 13E-17 (job-related calculations)
A 15-foot aluminum member warms by 100°F and the coefficient given is 0.0000128 inch per inch per degree. How much does it grow?
- a.About 0.12 inch
- b.About 0.0023 inch
- c.About 0.23 inch✓
- d.About 0.023 inch
The length is 180 inches and 180 × 0.0000128 × 100 = 0.230 inch. The 0.0023 shifts the decimal down two places, 0.023 shifts it down one, and 0.12 halves the result.CSLB C-17 study guide 13E-17 (job-related calculations)