Job Site Preparation

Protect the public and the property, correct what would make the new roof fail, and tear off what the code will not let you cover. CSLB weights this section at 13%. For worked examples, named traps and a full practice exam at CSLB's weights, see the PrepPass C-39 Roofing study guide.

Protecting surroundings

Materials are staged where they endanger no one, pedestrians get walkways and signs, and hot kettles are kept away from buildings and never placed on the roof.

Walkways
Pedestrian walkways at least 4 feet wide; construction railings at least 42 inches high.
2025 CBC 3306.2, 3306.4
Kettle location
At least 20 feet from combustibles and building openings; never inside or on the roof.
2025 CFC 303.2
Overhead lines
Treat every overhead conductor as energized until the owner verifies and visibly grounds it.
Cal. Code Regs. tit. 8 §2946(d)

Tear-off or recover

A new covering may go over an old one only in the situations the code lists, and never over a wet or deteriorated base, over slate or tile, or over two existing layers.

Two-layer limit
No recover where the roof already has two or more applications of any covering.
2025 CRC R908.4
Reuse
Undamaged slate or tile may be reinstalled; aggregate surfacing may not.
2025 CRC R908.5
Asbestos roofing
Remove intact where feasible, use wet methods, never drop or throw, and lower by the end of the shift.
Cal. Code Regs. tit. 8 §1529

Keep going: the full CSLB C-39 Roofing guide covers every section of the exam. CSLB C-39 Roofing Trade Exam Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Studying in order?

Practice stays free. The full CSLB C-39 Roofing study guide is the material itself, taught start to finish — a downloadable PDF + EPUB you keep.

Get the book — $24.99
Report