CSLB C-9 Drywall (Trade Exam) Exam Cheat Sheet (2026)

A free, printable CSLB C-9 Drywall (Trade Exam) exam cheat sheet: the 23 highest-yield points to know, grouped into 5 sections that follow the exam's content areas, each section with its published weight.

  • Free to read, print and keep — no signup, no email, no paywall.
  • 23 of the 23 points carry a citation to the rule they come from.
  • The real CSLB C-9 Drywall (Trade Exam) exam: 210 minutes.
  • Prints from your browser (Ctrl-P, or Cmd-P on a Mac) — the navigation, buttons and links drop out of the printed copy.
  • 100 free CSLB C-9 Drywall (Trade Exam) practice questions on the same material, every one explained.
  • Last updated: October 2026.

Planning and Estimating

18% of the exam
Study →
Rated walls
Build the listed design exactly: framing, board type, fasteners and joints.· 2025 CBC §703.2.1
Inspection before taping
Rated or shear gypsum assemblies are inspected after hanging and before taping.· 2025 CBC §110.3.6
Board width
Gypsum board is 48 inches wide; lengths vary by product.· UFGS 09 29 00
Markup vs margin
Markup is on cost; margin is on price: price = cost ÷ (1 − margin).· CSLB 13E-9 (computation questions)
Gypsum board
ASTM C1396; accessories ASTM C1047; tape and compound ASTM C474/C475.· 2025 CBC Table 2506.2
Steel framing
Nonstructural studs and track to AISI S220.· 2025 CBC Table 2506.2

Preparation, Framing, and Layout

14% of the exam
Study →
Weather protection
Board is not installed until weather protection is provided.· 2025 CBC §2508.2.1
Stocking
Sheetrock is not stacked on edge unless secured; keep material 6 ft from hoistways and 10 ft from open exterior edges.· T8 CCR §1549
Steel framing width
At least 1-1/4 inches in the least dimension; nonload-bearing per AISI S220.· 2025 CRC §R702.3.3
Fire barriers
Extend to the deck above and continue through ceiling spaces.· 2025 CBC §707.5
Grab bars
Bar, fasteners and supporting structure resist 250 lb at any point.· 2025 CBC §11B-609.8

Installation and Repair

32% of the exam
Study →
Wet texture on ceilings
Perpendicular application; 1/2 in at 16 in o.c., 5/8 in (or 1/2 in sag-resistant) at 24 in o.c.· 2025 CRC §R702.3.5
Screws
Into wood: Type W or S, 5/8 in penetration; thin steel: Type S, 3/8 in.· 2025 CRC §R702.3.5.1
Boxes in rated walls
Steel boxes up to 16 sq in; 100 sq in per 100 sq ft; 1/8 in maximum gap.· 2025 CBC §714.4.2
Garage under rooms
5/8-inch Type X ceiling.· 2025 CRC Table R302.6
Water-resistant board
Not over a vapor retarder in tub or shower compartments, nor where directly wet.· 2025 CBC §2509.3

Finishing

17% of the exam
Study →
Mesh tape
Do not use self-adhering mesh with drying-type compounds.· UFGS 09 29 00 §3.4
Level 5
A skim coat over the whole surface for gloss paint or critical light.· UFGS 09 29 00 §3.4.1
Dust
Use a vacuum sander or wet sanding.· USG joint compound data sheet

Safety

19% of the exam
Study →
Tailgate meetings
At least every 10 working days.· T8 CCR §1509(e)
Heat
Outdoor (§3395) and indoor (§3396) standards differ; the 10-minute-per-2-hours rest is agricultural.· T8 CCR §§3395, 3396
Asbestos
100 sq ft or more of ACM needs C-22 or asbestos certification.· B&P Code §7058.5
Rolling scaffolds
Base at least 1/3 the height free-standing; casters locked during work.· T8 CCR §1646

Now prove you know them

Reading an outline is not the same as recalling it under exam pressure. Drill the free CSLB C-9 Drywall (Trade Exam) questions to find the areas you keep missing, then sit a full timed mock.

Study aid, not a substitute for the official material — always confirm the current rule with CSLB — C-9 study guide (13E-9).