Public WorksQuestion 118 of 690
Before a contractor may bid on or be awarded a public works contract, the contractor must be registered with:
a.The CSLB only
b.The local building department
c.The Department of Industrial Relations (DIR)
d.The U.S. Department of Labor
Explanation
In addition to holding a CSLB license, a contractor must register annually with the DIR before bidding on or being awarded a public works contract.
Law Reference: Labor Code §1725.5Practice all 690 questions free — no signup required.
Related questions on this topic
- Prevailing wage requirements apply to public works projects with a contract value of at least:
- Who determines the prevailing wage rates that must be paid on a California public works project?
- On a public works project, contractors must submit certified payroll records to:
- The prevailing wage that must be paid on a public works project consists of:
- On a public works contract that exceeds $25,000, the prime contractor must furnish:
- An unpaid subcontractor on a public works project can compel the public agency to withhold project funds by serving:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review