Public WorksQuestion 125 of 1632

A contractor on a public works project must post the applicable prevailing wage determination:

a.At the contractor's principal office only
b.At the awarding body's own office only
c.At a conspicuous place at each job site
d.Nowhere; posting is not required

Explanation

Labor Code §1773.2 makes the awarding body specify the rates in the call for bids and the CONTRACTOR post the applicable determination at each job site, in a place the crew can see, so a worker can check the rate for their own craft. That split of duties is what option (b) gets wrong: the awarding body's own copy satisfies the awarding body's duty and puts nothing in front of the workers. The principal office fails for the same reason - the workers are not there. And posting is mandatory, so the last option states the opposite of the rule.

Law Reference: Labor Code §1773.2

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report