On a public works project, the bond that guarantees the project will be completed according to the contract is the:
Explanation
The performance bond runs to the public agency and guarantees that the work will be completed according to the contract, with the surety arranging completion or paying damages on a default. The payment bond required by Civil Code §9550 before work starts protects subcontractors and suppliers instead, since they cannot lien public property. The CSLB licence bond is a condition of licensure and answers to injured parties generally, not to this contract. The bid bond guarantees only that the successful bidder will sign and post the other bonds.
Law Reference: Public Contract Code §20170; Civil Code §9550This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- If a contractor pays less than the required prevailing wage on a public works project, the contractor may face:
- A contractor on a public works project must post the applicable prevailing wage determination:
- Which project is generally considered 'public works' subject to prevailing wage?
- A contractor's registration with the DIR to perform public works must be:
- On a covered public works project, prevailing wage must be paid to:
- On public works, the standard apprentice-to-journeyman ratio a contractor must meet is at least: