On a covered public works project, prevailing wage must be paid to:
Explanation
Labor Code §1772 treats every worker employed on a public work as employed on it, and §1774 binds the contractor and every subcontractor to pay not less than the prevailing rate. Union membership decides nothing, because the rate is set by craft and county. The minimum wage is a floor for all employment and has no bearing on who is owed the prevailing rate. Confining the duty to the prime's own payroll is the error §1774 exists to close, since most public works labour is subcontracted.
Law Reference: Labor Code §1772; §1774This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- Which project is generally considered 'public works' subject to prevailing wage?
- On a public works project, the bond that guarantees the project will be completed according to the contract is the:
- A contractor's registration with the DIR to perform public works must be:
- On public works, the standard apprentice-to-journeyman ratio a contractor must meet is at least:
- On a public works project, a worker who works more than 8 hours in a single day must generally be paid:
- Under Labor Code §1813, what penalty applies to a contractor for each worker for each day that worker is required to work more than the legal maximum hours without proper overtime pay on a public works project?