Contracts & ExecutionQuestion 143 of 690

When a contract is subject to the three-day right of cancellation, the contractor must give the buyer:

a.A verbal explanation of the cancellation right only
b.Nothing; the right is automatic and needs no paperwork
c.Two copies of a Notice of Cancellation form the buyer can use to cancel
d.A copy of the contractor's license

Explanation

The contractor must attach to the contract a properly completed Notice of Cancellation (typically two copies) that the buyer can complete and mail to exercise the three-day cancellation right.

Law Reference: Civil Code §1689.7