Excavated soil (spoil pile) and other materials must be kept at least how far from the edge of a trench?
Explanation
Section 1541(j)(2) requires excavated material and equipment to be kept at least 2 feet from the edge, OR held by retaining devices sufficient to stop them falling or rolling in, or by a combination of both. The alternative in the rule tells you what the setback is for: the spoil is a striking hazard AND a surcharge load whose weight presses down on the very wall it sits on, which is why a retaining device is an acceptable substitute for distance and why a berm of spoil is never a protective system. Six inches and one foot are too close to answer either problem. Four feet exceeds what the standard asks and is the figure a candidate reaches for by confusing the setback with a sloping offset.
Law Reference: 8 CCR §1541(j)(2)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- A contractor must ensure that a portable fire extinguisher on a construction site is:
- A general contractor on a multi-employer construction site is generally responsible for:
- When required to wear head protection on a construction site, a worker must use a:
- A trench excavation must be inspected by a competent person:
- A contractor receives a Cal/OSHA citation it believes is incorrect. The contractor's proper remedy is to:
- Section 2 of a 16-section Safety Data Sheet is titled "Hazard Identification." Which section would a worker check to find First-Aid Measures?
Last reviewed: · editorial process