Excavated soil (spoil pile) and other materials must be kept at least how far from the edge of a trench?
a.Right at the trench edge for convenience
b.6 inches from the edge
c.1 foot from the edge
d.At least 2 feet from the edge, or be restrained by other means
Explanation
8 CCR §1541 requires excavated material and equipment to be kept at least 2 feet back from the edge of an excavation, or otherwise restrained, to keep loads from falling on workers and adding surcharge load that can cause cave-ins.
Law Reference: 8 CCR §1541Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor must ensure that a portable fire extinguisher on a construction site is:
- A general contractor on a multi-employer construction site is generally responsible for:
- When required to wear head protection on a construction site, a worker must use a:
- A trench excavation must be inspected by a competent person:
- A contractor receives a Cal/OSHA citation it believes is incorrect. The contractor's proper remedy is to:
- Section 2 of a 16-section Safety Data Sheet is titled "Hazard Identification." Which section would a worker check to find First-Aid Measures?
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review