SafetyQuestion 394 of 690
A trench excavation must be inspected by a competent person:
a.Only once before the project starts
b.Only after a cave-in occurs
c.Daily before each shift, and as needed after rain or other conditions that increase hazards
d.Only when Cal/OSHA is on site
Explanation
8 CCR §1541.1 requires a competent person to inspect excavations, adjacent areas, and protective systems daily before each shift, and as needed throughout the shift after rainstorms or any occurrence that could increase hazards.
Law Reference: 8 CCR §1541.1Practice all 690 questions free — no signup required.
Related questions on this topic
- A general contractor on a multi-employer construction site is generally responsible for:
- When required to wear head protection on a construction site, a worker must use a:
- Excavated soil (spoil pile) and other materials must be kept at least how far from the edge of a trench?
- A contractor receives a Cal/OSHA citation it believes is incorrect. The contractor's proper remedy is to:
- Section 2 of a 16-section Safety Data Sheet is titled "Hazard Identification." Which section would a worker check to find First-Aid Measures?
- After identifying an unsafe condition on a job site, the IIPP standard requires the employer to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review