Business & LicensingQuestion 4 of 690
A contractor must notify the CSLB of a change in the qualifying individual (RME or RMO) within how many days?
a.30 days
b.60 days
c.90 days
d.180 days
Explanation
Contractors must notify CSLB within 90 days when the qualifier leaves, is replaced, or the business structure changes. Failure to notify can result in license suspension.
Law Reference: Bus. & Prof. Code §7076Practice all 690 questions free — no signup required.
Related questions on this topic
- A contractor who holds a Class "B" General Building Contractor license may perform work in which situation?
- What is the maximum amount of the Contractor License Bond required by the CSLB?
- A Responsible Managing Employee (RME) may qualify how many contractor licenses simultaneously?
- Which of the following business entities CANNOT hold a CSLB contractor license?
- A licensed contractor must display their license number on all of the following EXCEPT:
- If a contractor operates under a fictitious business name (DBA), the name must be:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review