Business & LicensingQuestion 4 of 163283% of test-takers answer this correctly

A contractor must notify the CSLB of a change in the qualifying individual (RME or RMO) within how many days?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

Contractors must notify CSLB within 90 days when the qualifier leaves, is replaced, or the business structure changes. Failure to notify can result in license suspension.

Law Reference: Bus. & Prof. Code §7068.2

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report