Business & LicensingQuestion 412 of 690

A contractor licensed as a partnership has one partner leave the business. The contractor must notify the CSLB of this change within:

a.10 days
b.30 days
c.There is no deadline to notify
d.90 days

Explanation

Under §7076, a contractor must notify the CSLB within 90 days of any change in personnel listed on the license, including the departure of a partner. The change in partnership membership affects the validity of the license.

Law Reference: Bus. & Prof. Code §7076