Business & LicensingQuestion 516 of 1605

A qualifier (RMO) leaves a contractor licensee on June 1. By what date must the licensee notify the Registrar of the disassociation to avoid automatic suspension of the license?

a.Within 90 days of the disassociation (by approximately August 30)
b.Within 30 days (by July 1)
c.Within one year (by the following June 1)
d.Notification is optional unless the Registrar requests it

Explanation

Under B&P §7068.2, when a qualifying individual is disassociated from a license, the licensee must notify the Registrar in writing within 90 days. Failure to do so or to replace the qualifier within the statutory window subjects the license to automatic suspension.

Law Reference: Bus. & Prof. Code §7068.2

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report