Business & LicensingQuestion 621 of 690

A Responsible Managing Officer (RMO) who is not a bona fide owner of the licensed entity must exercise direct supervision and control over the contractor's construction operations for at least how many hours per week?

a.20 hours per week
b.32 hours per week or 80% of the total hours per week the business is in operation, whichever is less
c.40 hours per week, with no exceptions
d.10 hours per week if the RMO qualifies multiple licenses

Explanation

Under Bus. & Prof. Code §7068.1 and CCR Title 16 §823, a qualifier who is NOT a bona fide owner of 10% or more of the licensed entity must exercise direct supervision and control of construction operations at least 32 hours per week OR 80% of the total hours the business operates per week, whichever is less. The 20-hour figure is incorrect; the 40-hour option ignores the 80%-of-operating-hours alternative; the 10-hour answer confuses qualifier duties with absent-qualifier arrangements, which are themselves a §7068.1 violation often called 'license renting.'

Law Reference: Bus. & Prof. Code §7068.1

Practice all 690 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Report