Insurance & LiensQuestion 80 of 690
Which of the following is NOT required to be included in a mechanics' lien?
a.Claimant's name and address
b.Social Security Number of the claimant
c.Description of the work performed
d.Amount of the claim
Explanation
A valid mechanics' lien must include the claimant's name/address, employer/employee info, description of work/materials, amount of claim, description of the property, and owner's name. No SSN is required.
Law Reference: Civil Code §8416Practice all 690 questions free — no signup required.
Related questions on this topic
- After recording a mechanics' lien, the claimant must file a lawsuit to enforce the lien within:
- What is the purpose of a "stop payment notice" on a private construction project?
- An owner can release a recorded mechanics' lien by obtaining a lien release bond equal to:
- On a public works project, a claimant who did not serve a preliminary notice can still file a:
- A general contractor typically has how many days after a Notice of Completion is recorded to file a mechanics' lien?
- The purpose of the preliminary notice requirement is to:
Last reviewed: · editorial process
PrepPass Editorial Team · Verified against California CSLB Contractor License Law & Business Exam · How we review