Insurance & LiensQuestion 82 of 1605

A general contractor typically has how many days after a Notice of Completion is recorded to file a mechanics' lien?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

The prime (direct) contractor has 60 days after the owner records a Notice of Completion to record a mechanics' lien. Subcontractors and suppliers have the shorter 30-day window.

Law Reference: Civil Code §8414