Insurance & LiensQuestion 82 of 163264% of test-takers answer this correctly

A general contractor typically has how many days after a Notice of Completion is recorded to file a mechanics' lien?

a.30 days
b.60 days
c.90 days
d.180 days

Explanation

The prime (direct) contractor has 60 days after the owner records a Notice of Completion to record a mechanics' lien. Subcontractors and suppliers have the shorter 30-day window.

Law Reference: Civil Code §8412(b)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report