A general contractor typically has how many days after a Notice of Completion is recorded to file a mechanics' lien?
a.30 days
b.60 days
c.90 days
d.180 days
Explanation
The prime (direct) contractor has 60 days after the owner records a Notice of Completion to record a mechanics' lien. Subcontractors and suppliers have the shorter 30-day window.
Law Reference: Civil Code §8412(b)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An owner can release a recorded mechanics' lien by obtaining a lien release bond equal to:
- Which of the following is NOT required to be included in a mechanics' lien?
- On a public works project, a claimant who did not serve a preliminary notice can still file a:
- The purpose of the preliminary notice requirement is to:
- A claimant recorded a mechanics' lien but was paid in full before filing a lawsuit. The claimant must:
- Which statement about a "joint check agreement" is correct?
Last reviewed: · editorial process
PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)