Business & LicensingQuestion 1438 of 1605

A prime contractor must generally pay a subcontractor its progress payment within how many days after receiving payment from the owner?

a.30 days
b.7 days
c.60 days
d.90 days

Explanation

Under B&P Code section 7108.5, a prime contractor must pay each subcontractor its share within seven days after receiving a progress payment, unless otherwise agreed in writing. Late payment can trigger penalties and discipline.

Law Reference: B&P Code §7108.5