Business & LicensingQuestion 1438 of 1605
A prime contractor must generally pay a subcontractor its progress payment within how many days after receiving payment from the owner?
a.30 days
b.7 days
c.60 days
d.90 days
Explanation
Under B&P Code section 7108.5, a prime contractor must pay each subcontractor its share within seven days after receiving a progress payment, unless otherwise agreed in writing. Late payment can trigger penalties and discipline.
Law Reference: B&P Code §7108.5Practice all 1605 questions free — no signup required.
Related questions on this topic
- Departing from accepted trade standards for good and workmanlike construction, as a willful violation, can lead to what?
- Willful or deliberate disregard of state or local building laws by a licensee is what?
- Diversion of funds or property received for a specific construction project, causing inability to complete it, is known as what violation?
- A home improvement contract must include the approximate start and completion dates. Failure to include required contract terms can result in what?
- Which practice by a home improvement contractor is expressly prohibited?
- During a declared state of emergency, contracting without a license for repair work may be charged as what?
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)