A supplier first delivered materials on Day 1 but served its preliminary notice on Day 40. For which materials may it claim?
Explanation
Civil Code §8204(a) provides that a claimant who did not give preliminary notice is not precluded from giving one later, but is then entitled to claim only for work performed within the 20 days prior to service of the notice, and at any time thereafter. Service on Day 40 therefore protects deliveries from roughly Day 20 forward, and the deliveries from Day 1 to Day 19 fall outside the window. (b) treats a late notice as fatal, which the subdivision expressly says it is not. (c) ignores the look-back altogether. (a) counts 20 days forward from service instead of backward, which protects nothing the statute protects.
Law Reference: Civ. Code §8204(a)This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An owner wants to be an additional insured on the contractor's policy. For the owner actually to have that status, the certificate must be accompanied by:
- A stop payment notice, unlike a mechanics lien, does NOT need to be:
- A contractor pays day laborers in cash, calls them independent contractors, and carries no workers' compensation. A laborer is injured. The contractor most likely:
- Which of the following is generally the LAST resort remedy because it requires foreclosing on real property?
- On a project where a notice of completion is recorded, missing the 30-day lien deadline (for a non-direct claimant) generally means:
- A general contractor's CGL policy typically will NOT respond to which claim?
Last reviewed: · editorial process