Public WorksQuestion 1584 of 1605
Competitive bidding on public works generally requires the public agency to award the contract to the:
a.Lowest responsible and responsive bidder
b.Highest bidder to ensure quality
c.Contractor located nearest the project
d.Contractor with the most experience regardless of price
Explanation
Public agencies typically must award to the lowest responsible, responsive bidder. 'Responsive' means the bid conforms to the solicitation; 'responsible' means the bidder is qualified and capable. This process promotes fairness and stewardship of public funds.
Practice all 1605 questions free — no signup required.
Related questions on this topic
- The primary state officer/agency responsible for enforcing prevailing wage laws and issuing civil wage-and-penalty assessments on public works is the:
- Because public property generally cannot be subjected to a mechanics lien, unpaid subcontractors on a California public works project are protected primarily by:
- The federal 'Miller Act' and its state counterpart 'Little Miller Acts' require, on public construction projects above threshold amounts, that the prime contractor furnish:
- A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)