Public WorksQuestion 1587 of 1605
Certified payroll records on a California public works project must generally be made available for inspection and, when requested, furnished to:
a.The general public's home addresses
b.Only the contractor's accountant
c.The DIR, the awarding public agency, and the Labor Commissioner
d.The CSLB Recovery Fund
Explanation
Labor Code §1776 requires certified payroll records to be available to the DIR, the awarding body, and the Division of Labor Standards Enforcement (Labor Commissioner). Certain personal information is redacted when copies go to the public, but enforcement agencies receive full records.
Law Reference: Labor Code §1776Practice all 1605 questions free — no signup required.
Related questions on this topic
- Competitive bidding on public works generally requires the public agency to award the contract to the:
- A contractor who pays workers LESS than the required prevailing wage on a public works project is subject to:
- Which of the following is the BEST definition of 'public works' for prevailing wage purposes?
- A subcontractor that is NOT registered with the DIR is listed on a bid for a public works project subject to prevailing wage. The likely consequence is that:
- When a contractor must pay 'per diem wages' at the prevailing rate, this generally includes:
- On a public works project, a 'bid bond' submitted with a contractor's bid primarily guarantees that:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)