On a private project, a subcontractor who has no direct contract with the owner must serve a Preliminary Notice on which parties to preserve mechanics lien rights?

a.The owner (or reputed owner), the direct contractor, and the construction lender (if any)
b.The direct (prime) contractor only
c.The construction lender only
d.The owner only

Explanation

Civil Code §8200 requires a claimant without a direct contract with the owner to serve the preliminary notice on the owner (or reputed owner), the direct contractor, and the construction lender, if any. Missing a required recipient jeopardizes lien and stop payment notice rights.

Law Reference: Civ. Code §8200

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report