Insurance & LiensQuestion 1468 of 1632

After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?

a.90 days after recording of the notice of completion
b.60 days after recording of the notice of completion
c.30 days after recording of the notice of completion
d.10 days after recording of the notice of completion

Explanation

Under Civil Code §8414, once a notice of completion (or cessation) is recorded, a claimant other than the direct contractor must record its lien within 30 days. The direct contractor gets 60 days after that notice. Absent any such notice, everyone has 90 days after completion.

Law Reference: Civ. Code §8414

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report