An unpaid framing subcontractor furnished labor and materials to a private remodel. Who is entitled to record a mechanics lien?
Explanation
Civil Code §8400 gives a lien right to a person that provides work authorized for a work of improvement, and lists the direct contractor, subcontractor, material supplier, equipment lessor, laborer, and design professional; §8404 defines authorized work as work requested or agreed to by the owner, or authorized by a direct contractor, subcontractor, architect, project manager, or other person having charge of part of the work. The framing subcontractor is squarely inside that. (b) is the limit that matters: a creditor who contributed nothing to the improvement, such as the contractor's landlord or lender, has no lien. (a) and (c) shrink the class to a single tier, which would leave every subcontractor and supplier without the remedy the chapter was written for.
Law Reference: Civ. Code §8400 / §8404This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →
Practice all 1632 questions free — no signup required.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Related questions on this topic
- An owner wants to remove a $60,000 mechanics' lien recorded against the property so the property can be sold or refinanced. Under Civil Code §8424, the owner may obtain a release of the lien by recording a lien release bond in the amount of:
- Claims against a contractor's $25,000 license bond total far more than $25,000: a residential homeowner claims $40,000, an unpaid framer claims $8,000 in wages, and a commercial property owner claims $30,000. Under Bus. & Prof. Code §7071.11, how is the bond distributed?
- A subcontractor's commercial general liability (CGL) policy provides 'additional insured' status to the prime contractor for the sub's negligent work. If a third party is injured and sues both the sub and prime, under California law:
- On a private project with NO notice of completion or cessation recorded, within what period after completion of the work of improvement must a direct (prime) contractor record its mechanics lien?
- After the owner records a valid Notice of Completion, within how many days must a SUBCONTRACTOR or material supplier record its mechanics lien?
- After a Notice of Completion is recorded on a private work of improvement, the DIRECT (prime) contractor must record its mechanics lien within: