Insurance & LiensQuestion 1466 of 1605

A framing subcontractor supplied labor and materials to a private residential remodel but was never paid. Which of the following best describes who is entitled to record a mechanics lien?

a.Only suppliers who delivered material directly to the owner
b.Any creditor of the contractor, whether or not they worked on the project
c.Only the direct (prime) contractor who signed the contract with the owner
d.Any person who, at the owner's request or the request of a person acting on the owner's behalf, provided labor, services, equipment, or material for a work of improvement

Explanation

Under Civil Code §8400, a person who provides work authorized for a work of improvement — including direct contractors, subcontractors, material suppliers, equipment lessors, and laborers — has a mechanics lien right. The framing sub qualifies. Mere creditors of the contractor who did not contribute to the improvement have no lien.

Law Reference: Civ. Code §8400

Practice all 1605 questions free — no signup required.

Related questions on this topic

Last reviewed: · editorial process

Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen Licensed California General Contractor (CSLB License #1101856 verify)
Report