Insurance & LiensQuestion 1553 of 1605
Which of the following must a valid recorded mechanics lien include?
a.A statement of the claimant's demand after deducting just credits and offsets
b.A copy of the workers' compensation policy
c.The owner's bank account number
d.The contractor's profit margin
Explanation
Civil Code §8416 requires the lien to state the amount of the claimant's demand after deducting all just credits and offsets, along with the owner's name, a description of the site, the claimant's name/address, and a proof of service on the owner.
Law Reference: Civ. Code §8416Practice all 1605 questions free — no signup required.
Related questions on this topic
- The primary function of a 'certificate of insurance' in the contracting process is to allow one party to:
- Under California's workers' compensation system, an employee injured on the job generally receives benefits:
- A contractor's 'umbrella' or 'excess' liability policy is designed to:
- A subcontractor who is added as additional insured on NO ONE's policy and carries its own CGL is protected for third-party claims:
- The construction lender must be served with a preliminary notice by a claimant lacking an owner contract primarily so the claimant can later:
- On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)