Business & LicensingQuestion 1612 of 1632

A licensed contractor moved its office on March 2 and mailed the Registrar the required written notice on August 20, well past the statutory window. What follows under Bus. & Prof. Code §7083?

a.The change is treated as effective on March 2, the date the business actually moved out
b.Nothing follows from the delay, because the change takes effect when the licensee mails it
c.The change takes effect the day headquarters receives the notice, and the delay is grounds for discipline
d.The license is suspended automatically until the Registrar approves the new business address

Explanation

Section 7083 gives the licensee 90 days from the change to notify the Registrar in writing on the board's form, and it attaches two consequences to a late notice. The change takes effect only on the date the written notification is received at the board's headquarters office, so the record is wrong for the whole intervening period. Separately, failing to notify within the 90 days is itself grounds for disciplinary action. A long window is not a soft one.

Law Reference: Bus. & Prof. Code §7083(a)-(c)

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report