Contracts & ExecutionQuestion 717 of 1605
A home improvement contract must be written in the same language principally used in the:
a.County where the property is located
b.Local building code
c.Contractor's license application
d.Oral sales presentation or negotiation
Explanation
B&P §7159 requires that the home improvement contract be written in the same language (for example, Spanish) that was principally used in the oral sales presentation or negotiation.
Law Reference: B&P §7159(c)Practice all 1605 questions free — no signup required.
Related questions on this topic
- When a homeowner properly exercises the three-day right to cancel a home improvement contract, the contractor must return any down payment within:
- A contractor and homeowner agree on a $9,000 bathroom remodel. The three-day right to cancel period generally begins:
- A contractor includes a clause in the home improvement contract stating the buyer waives their right to cancel. This clause is:
- Under §7159.5, a contractor may NOT do which of the following regarding down payments and progress payments?
- 'Joint control' in the context of a home improvement project refers to:
- When a home improvement contract's funds are handled through an approved joint control, the effect on the standard down payment and progress payment limits is that they:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)