Contracts & ExecutionQuestion 877 of 1605
A general contractor uses a subcontractor's bid to prepare and win the prime contract, reasonably relying on that bid. If the sub then tries to withdraw the bid, the general may argue the sub is bound under:
a.The parol evidence rule
b.Promissory estoppel, based on the general's reasonable reliance on the sub's bid
c.The Statute of Frauds only
d.A force majeure clause
Explanation
Courts have applied promissory estoppel to hold a subcontractor to its bid when a general contractor reasonably and foreseeably relies on that bid in preparing and submitting its own successful prime bid. The sub should expect such reliance, and injustice would result if the sub could freely withdraw after the general is committed. The parol evidence rule, the Statute of Frauds, and force majeure clauses do not address this reliance-based enforcement of a bid.
Practice all 1605 questions free — no signup required.
Related questions on this topic
- An 'incidental beneficiary' of a contract differs from an intended beneficiary in that an incidental beneficiary:
- A contractor's bid submitted to an owner is best characterized in contract terms as:
- 'Promissory estoppel' may allow enforcement of a promise, even without traditional consideration, when:
- A 'retention' (retainage) provision in a construction contract generally allows the owner to:
- A 'progress payment' schedule in a construction contract is designed to:
- A contract that is unfair and one-sided to the point of shocking the conscience, formed under grossly unequal bargaining power, may be held unenforceable as:
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)