Business FinancesQuestion 1122 of 1632

A framing job needs 3,200 board feet of lumber at $0.85 per board foot, plus 40 labor hours at $45/hour. What is the estimated direct cost?

a.$4,520
b.$3,920
c.$4,840
d.$2,720

Explanation

Materials are 3,200 x $0.85 = $2,720 and labour is 40 x $45 = $1,800, so the direct cost is $4,520. $3,920 comes from pricing the labour at $30 an hour instead of $45. $4,840 comes from reading the lumber at $0.95 a board foot. $2,720 is the materials alone, with the labour line left out of the estimate.

This topic, taught in full in the CSLB Law & Business guide. CSLB Law & Business — Complete Study Guide (2026) — PDF + EPUB, $24.99 · 14-day refund →

Practice all 1632 questions free — no signup required.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Related questions on this topic

Last reviewed: · editorial process

PrepPass team · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)
Report