Business FinancesQuestion 1123 of 1605
A contractor estimates a job at 120 labor hours. Actual hours worked were 150. By what percentage did labor hours exceed the estimate?
a.25%
b.15%
c.30%
d.20%
Explanation
Overrun = (actual - estimate) / estimate = (150 - 120) / 120 = 30 / 120 = 0.25 = 25%. Job costing compares estimated to actual to reveal a 25% labor overrun.
Practice all 1605 questions free — no signup required.
Related questions on this topic
- A contractor has $100,000 fixed costs and a contribution margin ratio of 25%. If he wants a $50,000 profit, what revenue is required?
- If a contractor's fixed costs rise while his contribution margin ratio stays the same, the break-even point will:
- A framing job needs 3,200 board feet of lumber at $0.85 per board foot, plus 40 labor hours at $45/hour. What is the estimated direct cost?
- The primary purpose of JOB COSTING is to:
- A concrete slab is 30 ft x 40 ft x 4 inches thick. How many cubic yards of concrete are needed? (1 cubic yard = 27 cubic feet)
- A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?
Last reviewed: · editorial process
Sen Lin, PrepPass Founder · Verified against California CSLB Contractor License Law & Business Exam · How we review
Reviewed by Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verify)