A contractor pays a mason $28/hour. With payroll burden (taxes, insurance, benefits) adding 35%, what is the fully burdened labor rate?

a.$28.00
b.$36.40
c.$37.80
d.$42.00

Explanation

Burden adds 35% to the base wage: $28 x 1.35 = $37.80 per hour. Estimators must use the fully burdened rate, not the base wage, or labor will be underestimated.