Professional Scrum Master I (PSM I) Practice Exam — All Questions

3 questions

Done & Scaling Basics

What does the Definition of Done create when it is met by an Increment?

  • a.Transparency about the quality and completeness of the work✓
  • b.Permission for the Scrum Master to close the Sprint
  • c.A guarantee that stakeholders will accept the product
  • d.A contract that fixes the scope of the next Sprint

The Definition of Done is a formal description of the state of the Increment when it meets the required quality. Meeting it creates transparency, so everyone shares an understanding of what 'done' work means.

Done & Scaling Basics

Who has the authority to cancel a Sprint?

  • a.The Product Owner, if the Sprint Goal becomes obsolete✓
  • b.Any stakeholder funding the product
  • c.The Scrum Master, if the team is behind schedule
  • d.The Developers, by majority vote

Only the Product Owner can cancel a Sprint. This may happen if the Sprint Goal becomes obsolete, for example due to a significant change in business direction. Sprint cancellations are uncommon and often traumatic.

Done & Scaling Basics

When multiple Scrum Teams work on the same product, what does the Scrum Guide 2020 say they should share?

  • a.The same Product Goal, Product Backlog and Product Owner✓
  • b.A single Scrum Master shared across all teams
  • c.Separate, independent Product Backlogs per team
  • d.One Sprint Backlog used by every team

If several Scrum Teams work on one product, they should share the same Product Goal, Product Backlog and Product Owner, keeping a single, transparent view of the product and its priorities.