Contratos y EjecuciónPregunta 789 de 1605
Which action would be considered a prohibited act tied to home improvement contracting?
a.Stating the license number in the contract
b.Giving the buyer two cancellation notices
c.Providing the buyer a signed copy before work starts
d.Deviating from or disregarding plans and specifications without the owner's written consent
Explicación
B&P §7161 lists departing from or disregarding the plans and specifications without the owner's written consent among prohibited acts and causes for disciplinary action.
Referencia Legal: B&P §7161Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A person solicits home improvement contracts for a contractor but is not registered as a home improvement salesperson. This person and the contractor:
- A home improvement contract is written entirely in English, but all negotiations were conducted in Spanish. Under §7159, the contract:
- A homeowner offers to prepay 100% of a $5,000 job to get a discount. Without a joint control, the contractor may lawfully accept a down payment of at most:
- Taken together, the home improvement contract rules of §7159 require all of the following EXCEPT:
- A homeowner emails a contractor, 'I'll pay you $8,000 to repaint my house.' The contractor emails back, 'I accept, but the price is $9,500.' Which statement best describes the legal effect of the contractor's reply?
- Which of the following is NOT one of the essential elements required to form a legally enforceable contract?
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)