Which action would be considered a prohibited act tied to home improvement contracting?

a.Stating the license number in the contract
b.Giving the buyer two cancellation notices
c.Providing the buyer a signed copy before work starts
d.Deviating from or disregarding plans and specifications without the owner's written consent

Explicación

B&P §7161 lists departing from or disregarding the plans and specifications without the owner's written consent among prohibited acts and causes for disciplinary action.

Referencia Legal: B&P §7161