Contratos y EjecuciónPregunta 829 de 1605

In the absence of a 'time is of the essence' clause or a specified completion date, a contractor is generally obligated to complete the work:

a.Only after full payment is received
b.Within exactly 30 days by law
c.Within a reasonable time under the circumstances
d.Whenever the contractor eventually chooses, with no limit

Explicación

When a contract does not specify a completion date or make time essential, the law implies that performance must occur within a reasonable time given the nature and circumstances of the work. The contractor cannot delay indefinitely, but a minor delay is not automatically a material breach. There is no automatic 30-day rule, and completion is generally not conditioned on receiving full payment in advance.

Practica las 1605 preguntas gratis — sin registro.

Preguntas relacionadas de este tema

Última revisión: · proceso editorial

Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen Licensed California General Contractor (CSLB License #1101856 verificar)
Reportar