Under the schedule-of-values method of progress billing, each payment application is based on:
a.A flat monthly fee regardless of progress
b.The contractor's overhead rate
c.The percentage of each line item of work completed to date
d.The sales tax collected that month
Explicación
A schedule of values breaks the contract price into line items. Each progress billing states the percentage of each item completed to date, and payment is the earned value less previous payments and retention. This ties billings directly to actual progress.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Progress billing (progress payments) means the contractor:
- On a home improvement contract, the down payment a contractor may collect is limited by law to whichever is less:
- On a home improvement contract, payments a contractor schedules and collects must:
- In California, sales or use tax on materials a contractor consumes to fulfill a construction contract is generally:
- The California minimum franchise tax that most corporations must pay to the Franchise Tax Board each year is:
- A sole proprietor contractor reports his business profit for federal income tax on:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)