Finanzas ComercialesPregunta 1194 de 1605
A contractor estimates a kitchen remodel: cabinets $8,000, countertops $3,500, labor $6,000, and permit $500. He adds a combined 22% for overhead and profit. What is the total price (nearest dollar)?
a.$21,960
b.$22,500
c.$18,000
d.$21,000
Explicación
Direct costs = $8,000 + $3,500 + $6,000 + $500 = $18,000. Overhead and profit = $18,000 x 22% = $3,960. Total = $18,000 + $3,960 = $21,960.
Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A contractor's monthly fixed costs are $8,000. His average job produces $500 contribution margin. How many jobs per month are needed to break even?
- A line of credit is most useful to a contractor for:
- A contractor's accounts receivable total $180,000 and annual credit sales are $1,080,000. Roughly how many days does it take on average to collect (days sales outstanding)?
- A contractor's gross profit is $120,000 and overhead is $95,000. What is his net profit?
- A change order adds $3,200 of direct cost to a job. If the contractor applies his standard 30% markup, how much should the change order add to the contract price?
- A written, signed change order is important because it:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)