SeguridadPregunta 1301 de 1605
Which is a required control when performing higher-risk (Class I) asbestos removal?
a.Regulated areas, negative-pressure enclosures, wet methods, and respiratory protection
b.No controls if done quickly
c.Only a paper dust mask
d.Open-air dry removal
Explicación
Class I asbestos work requires stringent controls: regulated areas, critical barriers/negative-pressure enclosures, wet methods, HEPA filtration, and appropriate respirators to prevent fiber release.
Referencia Legal: 29 CFR 1926.1101Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- Under the silica standard, employers must also establish and implement a:
- Before renovation or demolition of an older building, the standard approach to potential asbestos-containing materials (ACM) is to:
- The permissible exposure limit for asbestos is 0.1 fiber per cubic centimeter as an 8-hour TWA. Work disturbing asbestos is organized into:
- When workers may be exposed to lead during construction (e.g., disturbing lead-based paint), the employer must initially:
- The OSHA permissible exposure limit for lead in construction is:
- For lead work above the action level, the employer must provide hygiene facilities so workers can:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)