SeguridadPregunta 1317 de 1605
Before a crane is used on a shift, who must conduct a documented inspection of the equipment?
a.The delivery driver
b.No one — cranes never need inspection
c.A competent person, who performs each-shift and more detailed periodic inspections
d.The building owner
Explicación
1926.1412 requires a competent person to inspect the crane before each shift and to conduct/oversee more detailed monthly and annual inspections, checking control mechanisms, wire rope, hooks, and safety devices.
Referencia Legal: 29 CFR 1926.1412Practica las 1605 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- The heat illness standard requires the employer to maintain a written Heat Illness Prevention Plan that is:
- When a worker shows signs of heat illness such as confusion or fainting, the employer's emergency response must include:
- Under OSHA's construction crane standard, operators of most cranes with a rated capacity over 2,000 pounds must be:
- To protect ground workers from a crane's rotating superstructure (swing radius), the employer must:
- Rigging equipment for material handling (slings, chains, hooks) must be:
- During crane operation, if the operator is engaged in a lift and needs to leave the controls, they must:
Última revisión: · proceso editorial
Sen Lin, Fundador de PrepPass · Verificado con California CSLB Contractor License Law & Business Exam · Cómo revisamos
Revisado por Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — verificar)