Theory & SafetyPregunta 116 de 120
A 480-volt panelboard is mounted on a wall with a grounded concrete wall directly behind the working space. What is the minimum depth of working space?
a.2 and 1/2 feet
b.3 feet
c.4 feet
d.3 and 1/2 feet
Explicación
For nominal voltages of 151 to 600 volts to ground, Condition 2 exists when exposed live parts face a grounded surface such as a concrete or masonry wall, and the required depth is 3 and 1/2 feet. Condition 1, with no live or grounded parts opposite, requires 3 feet, and Condition 3, with exposed live parts on both sides, requires 4 feet.
Referencia Legal: 2023 NEC §110.26(A)(1)Practica las 120 preguntas gratis — sin registro.
Preguntas relacionadas de este tema
- A balanced delta-connected load has a phase current of 20 amperes. What is the line current?
- A single-phase transformer has a 480-volt primary and a 120-volt secondary. If the secondary carries 100 amperes, what is the approximate primary current?
- What is the secondary full-load current of a 25 kVA single-phase transformer with a 240-volt secondary?
- What is the minimum width of working space in front of electrical equipment?
- Entrances at each end of the working space are generally required for equipment rated at least what value and over 6 feet wide?
- The dedicated equipment space above a panelboard extends from the top of the equipment to what height?
Última revisión: · proceso editorial
Equipo Editorial de PrepPass · Verificado con Journeyman Electrician Licensing Exam (NEC-based) · Cómo revisamos