SafetyCâu 665 / 700

Before mechanized digging begins, an excavator must have underground utilities located and marked. In California, what is the general requirement for notifying the regional notification center (DigAlert / 811)?

a.Notify the utility owner within 24 hours after digging starts
b.Contact the regional notification center at least two working days before excavating so utilities can be marked
c.No notice is needed if the dig is under 5 feet deep
d.Call only if the excavator personally believes a line is present

Giải thích

Correct: California law requires contacting the regional notification center (DigAlert / 811) generally at least two working days before excavating so member utilities can locate and mark their lines. Notifying after digging starts, skipping notice for shallow digs, or relying on personal judgment all violate the advance-locate requirement and risk striking gas, electric, or other buried lines.

Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội Ngũ Biên Tập PrepPass · Đối chiếu với California CSLB General Building (B) Trade Examination · Quy trình kiểm tra
Báo lỗi