Workers will enter a 7-foot-deep excavation next to a former solvent storage area where a hazardous atmosphere could exist. Under Cal/OSHA, what is required before and during entry?
a.Nothing special, because open excavations always have fresh air
b.Test only once at the start of the shift and assume conditions stay safe
c.Test the atmosphere for oxygen level and hazardous gases before entry and as often as needed, and provide controls such as ventilation where a hazard could exist
d.Rely on workers noticing symptoms and leaving on their own
Giải thích
Correct: where a hazardous atmosphere could reasonably exist in an excavation deeper than 4 ft (near contamination, fuels, or where oxygen may be deficient), the atmosphere must be tested before entry and regularly thereafter, with controls like ventilation and emergency provisions. Assuming fresh air, testing only once, or waiting for symptoms all fail to protect against odorless, invisible hazards.
Luyện miễn phí toàn bộ 700 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- A contractor wants to use a benched (stepped) excavation wall as the protective system. In which soil is benching NOT permitted?
- CALCULATION: A trench 5 feet deep and 100 feet long requires a means of egress so no worker travels more than 25 feet of lateral distance to reach a ladder. What is the MINIMUM number of ladders needed, spaced so every point is within that distance?
- Before mechanized digging begins, an excavator must have underground utilities located and marked. In California, what is the general requirement for notifying the regional notification center (DigAlert / 811)?
- During lockout/tagout (LOTO) on a jobsite, several workers each apply their own personal lock to an energy-isolating device. Who is authorized to remove a given worker's lock?
- Cal/OSHA gives employers two accepted ways to protect workers from ground faults when using temporary power for hand tools. What are they?
- Equipment will operate near an overhead power line energized at 50 kV or less. What MINIMUM clearance must be maintained between the line and any part of the equipment or load, absent other controls?
Cập nhật gần nhất: · quy trình kiểm tra