Kinh doanh & Cấp phépCâu 1438 / 1632

On a private project, a prime contractor must generally pay a subcontractor its share of a progress payment within how many days after receiving that payment from the owner?

a.30 days
b.7 days
c.60 days
d.90 days

Giải thích

Under B&P Code section 7108.5 a prime contractor must pay each subcontractor its share within seven days after receiving a progress payment from the owner (b). Wrongful withholding carries a 2%-per-month penalty plus attorney's fees and is grounds for discipline. (a) 30 days and (d) 90 days are commercial terms, not the statute's. (c) 60 days is the Public Contract Code §7107 window for a public agency to release retention after completion — a different rule for a different project type. The 10-day figure candidates often reach for is Civil Code §8814, which governs passing RETENTION through to a subcontractor, not progress payments.

Trích dẫn luật: B&P Code §7108.5

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi