Kinh doanh & Cấp phépCâu 1439 / 1605
A home improvement contract must include the approximate start and completion dates. Failure to include required contract terms can result in what?
a.A larger down payment
b.Automatic license upgrade
c.No consequence
d.Disciplinary action, with omitted terms unenforceable against the consumer
Giải thích
Under B&P Code section 7159, home improvement contracts must contain specified terms including dates and notices. Omitting required elements is a violation subject to discipline and can render provisions unenforceable against the consumer.
Trích dẫn luật: B&P Code §7159Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Willful or deliberate disregard of state or local building laws by a licensee is what?
- Diversion of funds or property received for a specific construction project, causing inability to complete it, is known as what violation?
- A prime contractor must generally pay a subcontractor its progress payment within how many days after receiving payment from the owner?
- Which practice by a home improvement contractor is expressly prohibited?
- During a declared state of emergency, contracting without a license for repair work may be charged as what?
- Which statement about the contractor's license bond is correct?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)