Bảo hiểm & Quyền cầm giữCâu 1478 / 1632
On a private commercial project the direct contractor furnishes a payment bond. Its primary purpose is to:
a.Protect the owner against defective workmanship
b.Guarantee the project is completed on schedule
c.Reimburse the owner's construction financing costs
d.Guarantee payment to subs, laborers and suppliers
Giải thích
A payment bond guarantees payment down the chain: §8608 gives the right of recovery to claimants who provided work to the direct contractor, directly or through one or more subcontractors, and §8612 conditions the claim on the preliminary notice the lien law requires. (a) and (b) both describe a performance bond, which answers to the owner for completion and quality — the two bonds are usually bought together and confusing them is the classic error. (c) is not a bonded obligation at all; financing costs are the owner's own.
Trích dẫn luật: Civ. Code §8608 / §8612Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.
Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →
Câu hỏi liên quan cùng chủ đề
- After recording a mechanics lien, within what period must the claimant file a lawsuit (action) to foreclose the lien, or the lien becomes unenforceable?
- A 'stop payment notice' (formerly 'stop notice') is a remedy that allows an unpaid claimant to reach:
- On a private work with a construction lender, for a stop payment notice to bind the LENDER to withhold funds, the claimant generally must:
- California law makes which insurance mandatory for a contractor that has employees?
- A licensed contractor holds a C-39 roofing classification and has no employees. Under B&P §7125 as it reads until January 1, 2028, the contractor must:
- The main purpose of a contractor's Commercial General Liability policy is to cover:
Cập nhật gần nhất: · quy trình kiểm tra
Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)