Bảo hiểm & Quyền cầm giữCâu 1491 / 1605
Which event does NOT constitute 'completion' of a work of improvement for purposes of starting mechanics lien deadlines on a private project?
a.Cessation of labor for a continuous period of 60 days
b.Occupation or use by the owner accompanied by cessation of labor
c.Actual completion of the work of improvement
d.The contractor mailing its final invoice to the owner
Giải thích
Civil Code §8180 defines completion to include actual completion, occupation/use plus cessation of labor, acceptance by the owner, or cessation of labor for 60 continuous days. Merely mailing a final invoice is not a statutory completion event.
Trích dẫn luật: Civ. Code §8180Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- Under current California law, a mechanics lien is generally NOT enforceable unless the claimant:
- An owner who learns that work is being done on their property without their authorization (e.g., by a tenant) can limit exposure to mechanics liens by recording and posting a:
- To be effective, a Notice of Non-Responsibility must generally be posted on the property and recorded within how many days after the owner obtains knowledge of the work of improvement?
- A 'notice of cessation' may be recorded by an owner when labor has ceased on the work of improvement for a continuous period of at least:
- The party who purchases a surety bond and whose performance is guaranteed is called the:
- On a bond, the party who is protected and can make a claim if the principal defaults is the:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)