Compared to a mechanics lien, a key ADVANTAGE of a stop payment notice for a lower-tier claimant is that it:

a.Needs no bond, whoever the notice is served upon
b.Requires no preliminary notice, since it reaches money only
c.Reaches undisbursed funds without a foreclosure suit
d.Runs against the owner personally, beyond the unpaid funds

Giải thích

A stop payment notice traps money the owner or lender has not yet paid out, so the claimant is paid from the construction fund instead of having to sue to foreclose on and sell the owner's property. (a) is half-true and therefore the best trap: a notice given to the OWNER under §8520 needs no bond, and §8522(a) obliges the owner to withhold on receipt, but a notice that binds a construction lender must be accompanied by a bond of 125 percent of the claim under §8532. (b) is wrong — the same preliminary notice that preserves lien rights conditions the stop payment notice. (d) overstates the remedy: it reaches the fund, and an owner who has already properly disbursed everything has nothing left to withhold.

Trích dẫn luật: Civil Code §8520 / §8522(a) / §8532

Luyện miễn phí toàn bộ 1632 câu hỏi — không cần đăng ký.

Own the complete CSLB Law & Business guide — PDF + EPUB, $24.99 →

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Đội ngũ PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)
Báo lỗi