A notice of completion was recorded on July 1. An unpaid drywall subcontractor wants to record a mechanics lien. The last day to record is approximately:
a.July 5
b.August 30 (60 days)
c.September 29 (90 days)
d.July 31 (30 days)
Giải thích
Under Civil Code §8414, once a notice of completion is recorded, a claimant other than the direct contractor must record within 30 days. Counting 30 days from July 1 lands at the end of July. Only the direct contractor would get 60 days.
Trích dẫn luật: Civ. Code §8414Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- An 'indemnitor' in a hold-harmless agreement is the party who:
- Best practice is to serve the Preliminary Notice at the START of a project even if payment is currently on time, because:
- Which statement about surety bonds is TRUE?
- The 'your work' exclusion common in CGL policies means the policy generally will NOT pay to:
- A mechanics lien attaches to:
- When an owner is added as an 'additional insured' on the general contractor's liability policy, which document actually grants that status?
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)