An equipment rental company rents a crane to a subcontractor on a private project. To preserve a mechanics lien for unpaid rental charges, the rental company should:

a.Do nothing, since equipment lessors have automatic liens
b.Serve notice only on the subcontractor
c.Serve a preliminary notice on the owner, direct contractor, and construction lender within 20 days of first furnishing
d.Record a lien before delivering the crane

Giải thích

Equipment lessors that provide equipment for a work of improvement have lien rights but, lacking a direct owner contract, must serve a preliminary notice on the owner, direct contractor, and lender within 20 days of first furnishing under Civil Code §8200 to preserve those rights.

Trích dẫn luật: Civ. Code §8200

Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.

Câu hỏi liên quan cùng chủ đề

Cập nhật gần nhất: · quy trình kiểm tra

Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen Licensed California General Contractor (CSLB License #1101856 kiểm tra)
Báo lỗi