A direct contractor completed a private remodel on March 1. No notice of completion was ever recorded and the owner never occupied. The contractor's last day to record a mechanics lien is approximately:
a.March 11 (10 days)
b.March 31 (30 days)
c.May 30 (90 days)
d.April 30 (60 days)
Giải thích
With no notice of completion or cessation recorded, Civil Code §8412 gives the direct contractor 90 days from completion to record. Counting 90 days from March 1 lands near the end of May.
Trích dẫn luật: Civ. Code §8412Luyện miễn phí toàn bộ 1605 câu hỏi — không cần đăng ký.
Câu hỏi liên quan cùng chủ đề
- On a public works project, subcontractors generally CANNOT record a mechanics lien against the public property. Their principal payment security instead is the:
- After an owner records a lien release bond of 125%, an unpaid subcontractor who wants to be paid must now pursue:
- 'Employers' liability' coverage, usually part of a workers' compensation policy, protects the employer against:
- Requiring a subcontractor to provide a certificate of insurance BEFORE it starts work is a best practice primarily because it:
- Which best describes the difference between the payment bond and the performance bond on the SAME project?
- A mechanics lien on a private project should describe the property with:
Cập nhật gần nhất: · quy trình kiểm tra
Sen Lin, Người sáng lập PrepPass · Đối chiếu với California CSLB Contractor License Law & Business Exam · Quy trình kiểm tra
Người kiểm duyệt Abraham Chen — Licensed California General Contractor (CSLB License #1101856 — kiểm tra)